====== EVSX ====== | ====== EVSX ====== | ||
- | EVSX is a subsidiary of St-Georges Eco-Mining, first announced in January of 2021. ((https://www.thenewswire.com/press-releases/ | + | EVSX is a subsidiary of St-Georges Eco-Mining, first announced in January of 2021. ((https://webfiles.thecse.com/SX_Press_Release_-_January_20_2021_-_Paul_Pelosi_Jr_Named_President_of_St-Georgess_Subsidiary.pdf)) The stated goal of EVSX is to " |
- | EVSX is intended to be a source of blackmass through its operations, and this blackmass in turn is intended to supply [[sxm|SXM]].((https:// | + | EVSX is intended to be a source of blackmass through its operations, and this blackmass in turn is intended to supply [[sxm|SXM]].((https:// |
+ | |||
+ | ===== Partnerships ===== | ||
+ | |||
+ | ==== Call2Recycle ==== | ||
+ | |||
+ | > We will be seeing volume increases, we believe, from that supply agreement as soon as we're commissioned, | ||
+ | -[[ian_peres|Ian C. Peres]] ((https:// | ||
===== Facilities ===== | ===== Facilities ===== | ||
Line 10: | Line 17: | ||
EVSX operates a battery-recycling facility based in the Thorold Multimodal Hub, in Thorold, Ontario. | EVSX operates a battery-recycling facility based in the Thorold Multimodal Hub, in Thorold, Ontario. | ||
+ | |||
+ | > The Thorold location that we have is, to me, probably one of the most ideal locations in Canada. It's located in the Golden Horseshoe and it's in one of the most populated hubs in the country. So, you know, we're centrally located in the largest automotive cluster in North America. We've got 35,000 square feet, which is right in - I think a some-400-acre multimodal industrial complex. We're adjacent to the Welland Canal, we have access to rail, ... in terms of location to install a plant, I really don't think it gets better. | ||
+ | -[[ian_peres|Ian C. Peres]] ((https:// | ||
+ | |||
{{: | {{: | ||
Line 18: | Line 29: | ||
==== Multi-chemistry line ==== | ==== Multi-chemistry line ==== | ||
- | > EVSX has three very highly-automated processing lines ... It's a line that can actually process the recycling of batteries with very minimal labour. The batteries drop into one section of the line. They go through a series of hammers and shredders and shaking tables and so on - magnetic separation and so on. The paper is separated from the plastic, the metals, the steel, the aluminum, and the battery metals (so the nickel, the cobalt, etc.). What we do is we effectively repurpose all of those materials back into the supply [chain] ... We're able to process well over 16 types of different types of battery chemistries. Irregular batteries (like batteries that are too small), batteries that are deemed to be too resource-intensive by certain processors - we can virtually do anything, so alkaline, nickel-cadmium, | + | > EVSX has three very highly-automated processing lines ... It's a line that can actually process the recycling of batteries with very minimal labour. The batteries drop into one section of the line. They go through a series of hammers and shredders and shaking tables and so on - magnetic separation and so on. The paper is separated from the plastic, the metals, the steel, the aluminum, and the battery metals (so the nickel, the cobalt, etc.). What we do is we effectively repurpose all of those materials back into the supply [chain] ... We're able to process well over 16 types of different types of battery chemistries. Irregular batteries (like batteries that are too small), batteries that are deemed to be too resource-intensive by certain processors - we can virtually do anything, so alkaline, nickel-cadmium, |
- | [[https:// | + | -[[ian_peres|Ian C. Peres]] |
{{ : | {{ : | ||
Line 55: | Line 66: | ||
==== 2022 ==== | ==== 2022 ==== | ||
- | In March of 2022, the company announced that they had eliminated their initial Baie-Comeau location secured in June of 2021. Instead, they planned to work with the municipality to secure alternate sites at a fraction of the cost. Meanwhile, EVSX announced its intent to begin recycling nickel-cadmium batteries, and a search for a suitable site was to be undertaken at various locations in Québec and Ontario.((https:// | + | In March of 2022, the company announced that they had eliminated their initial Baie-Comeau location secured in June of 2021. Instead, they planned to work with the municipality to secure alternate sites at a fraction of the cost. Meanwhile, EVSX announced its intent to begin recycling nickel-cadmium batteries, and a search for a suitable site was to be undertaken at various locations in Québec and Ontario.((https:// |
In April of 2022, it was announced that the board of St-Georges had voted to authorize EVSX to move forward with its battery recycling plan. At that time, this plan involved acquiring a facility in Baie-Comeau, | In April of 2022, it was announced that the board of St-Georges had voted to authorize EVSX to move forward with its battery recycling plan. At that time, this plan involved acquiring a facility in Baie-Comeau, | ||
Line 69: | Line 80: | ||
==== 2024 ==== | ==== 2024 ==== | ||
- | In March of 2024 EVSX was granted an Environmental Compliance Approval for operating the alkaline battery line at Thorold, | + | In March of 2024 EVSX was granted an Environmental Compliance Approval for operating the alkaline battery line at Thorold, |
On July 17th, St Georges Eco-Mining and Call2Recycle Canada jointly announced the operational launch of EVSX's battery processing plant in Thorold, Ontario.((https:// | On July 17th, St Georges Eco-Mining and Call2Recycle Canada jointly announced the operational launch of EVSX's battery processing plant in Thorold, Ontario.((https:// | ||
Line 76: | Line 87: | ||
On November 5th, EVSX announced that they had " | On November 5th, EVSX announced that they had " | ||
- | ((https:// | + | ((https:// |
Later that month, EVSX announced that they had commenced the installation of one of their three multi-chemistry lines within the Thorold facility. ((https:// | Later that month, EVSX announced that they had commenced the installation of one of their three multi-chemistry lines within the Thorold facility. ((https:// | ||
Line 82: | Line 93: | ||
On December 24th, EVSX announced that they had completed installation of the first multi-chemistry line in the Thorold facility. ((https:// | On December 24th, EVSX announced that they had completed installation of the first multi-chemistry line in the Thorold facility. ((https:// | ||
+ | ==== 2025 ==== | ||
+ | |||
+ | On February 6th, EVSX announced that during the process of commissioning the multi-chemistry line, they updated the facility' | ||
+ | |||
+ | On March 5th, EVSX announced that they have secured the final environmental compliance approval needed to commence battery-recycling operations using the multi-chemistry line.((https:// | ||
+ | |||
+ | On March 12th, EVSX announced that they have secured a three-year battery supply agreement with [[call2recycle|Call2Recycle]]. This agreement includes both an increase in battery volumes and an expansion in allowable battery types.((https:// | ||